Proyek Rumah Susun ini milik Dinas Perumahan Rakyat dan Kawasan Permukiman Pemerintah Provinsi DKI Jakarta. Progres terkini proyek tsb sudah mencapai 7,5 %. Untuk list pekerjaannya saat ini Bored Pile Tower A sudah selesai, Tower B kurang 27 titik, Tower A sudah mencapai Pile Cap dan Tie Beam. Demi kelangsungan kesehatan karyawan, protokol kesehatan terus diterapkan. Walaupun ditengah pandemi, tidak ada halangan bagi kami untuk terus memberikan karya terbaik untuk masyarakat dan Indonesia.